Bus Systems – Retrofit Older GIS Installs

Substations often require new equipment to upgrade or expand existing facilities or replace damaged systems. This often requires interfacing to equipment from varying manufactures and technologies of existing equipment.

In the case of a retrofit to an existing gas insulated switchgear substation, the ability to design and install a variety of interfaces, and to allow sufficient installation tolerance is paramount. The existing equipment may include GIS supplied by different manufacturers who may adhere to contrasting philosophies and operating parameters.

In other retrofit cases, outdated equipment must be replaced. Again, the challenge remains to minimize the outage time required to implement the change and to utilize as much existing peripheral equipment at possible to reduce costs. Avail High Voltage Bus Systems provides solutions to the problems faced when retrofitting or extending existing systems and offers turnkey installations and commissioning.

Project Profile: Consolidated Edison Dunwoodie Station (Yonkers, New York)

The Dunwoodie substation, commissioned in 1974, functioned well until 1988, when an oil cable fire destroyed a circuit breaker, the adjacent oil pot heads, interconnecting breaker bus and disconnects.

In rapid response to Consolidated Edison’s emergency requirements, Avail provided interconnecting breaker bus to bypass the damaged breaker position and re-energize the ring. The Avail bus left future expansion capabilities to interface to a new circuit breaker position that would be supplied at a later date. The interconnecting bus required interface to existing ITE bus. Avail High Voltage Bus Systems was the only manufacturer that could respond to this emergency.

Seabrook Nuclear Power Plant Substation (Seabrook, New Hampshire)

The Seabrook gas insulated substation project, consisting of 345 kV ITE GIS and bus, had developed a history of unreliability due to leaks and insulator failures within the bus. This was particularly a cause of concern within areas of the substation that were not protected by redundant sections of the installation, thereby having no backup in case of section bus failures.

Avail bus, backed by its established record of reliability in long-term service, was selected to replace the ITE bus for these critical connections. They involved connections from the GIS to both main transformers and to auxiliary transformers.

In addition to offering a reliable bus design, Avail High Voltage Bus Systems defined and managed a schedule to complete the installation within a one-week outage to comply with the NRC approved outage schedule, and under tight space and access conditions.

The first of the Seabrook Avail bus installations has been in service without fault since its completion in 1990.

Contact Us

Request More Information

Request More Information

To receive a quote or request additional information, please complete the form below and we will contact you as soon as possible. Fields marked with an asterisk (*) are required.

Email Signup

Sign up to receive the latest news from Avail Infrastructure Solutions

Share This
Skip to content